Warning: "continue" targeting switch is equivalent to "break". Did you mean to use "continue 2"? in /home/carrcivilenginee/public_html/wp-content/plugins/revslider/includes/output.class.php on line 3706

Warning: "continue" targeting switch is equivalent to "break". Did you mean to use "continue 2"? in /home/carrcivilenginee/public_html/wp-content/plugins/all-in-one-seo-pack/modules/aioseop_opengraph.php on line 848
PO86 Arc Strike Investigations & Epoxy Shell Installation – Carr Civil Engineering

PO86 Arc Strike Investigations & Epoxy Shell Installation

Due to a recent heath fire,  multiple plumes of  dense, thick, acrid smoke rose up into the high voltage overhead power cables, resulting in multiple arc strikes travelling back down through the carbon within the smoke,  striking the HP Pipeline parallel to the high voltage overhead cables.

After excavations were carried out & the pipeline had been surveyed by the client via a P11 assessment, the results of this were sent off to a third party mechanical damage expert, and they advised that an epoxy repair shell should be fitted to the pipeline. See below photographs.

Arc strike found

P11 Assessment

Epoxy shell blasted to specification.

Epoxy shell being centralised.

Epoxy shell being filled.

Recoated shell to client specification.

 

Recent Posts

Remove Broken Paving Slabs at Frensham AGI

5 years ago

Crowthorne Reinstatement Project

5 years ago

Lordswood Pressure Regulation Site (PRS)

5 years ago

Our Projects

Carr Civil Engineering

  • 4 Longham Business Centre, 168 Ringwood Rd, Ferndown Dorset BH22 9BU
  • +44 (0) 1202 578697
  • 8.30am - 4.30pm