We were called into carry out works at Frensham AGI, the works consisted of lifting sunken & broken slabs, which were causing a trip hazard for people entering the site compound. We were issued a Form of Authority & Safe Working Procedures were put into place for working on or near buried pressurised pipework, PAMS were used at all times, with suitable PPE.
The works consisted of site set up with barriers, fire extinguishers & breathing apparatus in place. Once the slabs were removed it had been agreed that a concrete base would be laid, the ground was levelled and hardcore laid, whacked and sealed, with a timber framework constructed, concrete was brought in via wheelbarrow and brush finished.
]]>
Roger Stace the Land Manager (Conservation) for Berkshire advised the below:
“I was on site today and have looked at the work Sean and the team had done and am very pleased with the results. Thank you for the teams efforts”
]]>
Full health & Safety pack, PPE, Hand and Vibration monitoring, due to use of hand power tools.
A permit to work was put in place by the client.
]]>All parties were happy with the project and the way it had been reinstated, and we have agreed with our client to cut down some heather & reseed the area as a goodwill gesture to the councils & Natural England for being so accommodating.
Comments from Natural England, Des Sussex – Team Leader
“This sounds very good – many thanks for taking the nature conservation interests of the site into account with your management of the project. I hope the future management plans will help to safeguard the pipeline as well as the habitats”
]]>
]]>
Once the end seal and filling points were exposed, the sleeve was then pressurised, and it was found that the end seal was offset and not holding pressure. A decision was made by the client that a bespoke end seal was to be manufactured and installed. Once the endseal was installed the sleeve was then repressurised with nitrogen and is now holding pressure, resulting in the sleeve now being compliant.
]]>
This will be revolutionary for Carr Civil’s as means less paper ( good for the environment) all information will be on tablet & will allow us to give detailed information straight to the client!
Please keep following, for more info!!
]]>
]]>
The digging methodology used on this project was a stepped battered excavation, hand digging within 1 metre from the side of the pipeline, due to the project being under SW2 permitry.
]]>
After excavations were carried out & the pipeline had been surveyed by the client via a P11 assessment, the results of this were sent off to a third party mechanical damage expert, and they advised that an epoxy repair shell should be fitted to the pipeline. See below photographs.
Arc strike found
P11 Assessment
Epoxy shell blasted to specification.
Epoxy shell being centralised.
Epoxy shell being filled.
Recoated shell to client specification.
]]>